The following letter was sent to the residents of the Goldthorpe building.
The original document can be found on this link.
Hertel (UK) Ltd
Unit 6C Heathrow Corporate Park
Green Lane
Hounslow
TW46ER
Tel: 01989561 679
Fax: 0208 572 8229
env.div@hertel.co.uk
www.hertel.co.uk
YourRef:
Our Ref: PT78693/DC
Date: 07-09-11
The Occupier
Goldthorpe
PLANNED WORKS
Dear Sir/Madam
Hertel have been instructed by The Apollo Group working on behalf of London Borough of Camden to carry out the Upgrading/Replacement works to the communal cold-water storage cistern (s) supplying your property. We propose to carry out this work Thursday 08th September 2011. These works are part of planned periodic maintenance of the water tanks.
We will not require access into your property to complete these works.
To enable us to carry out this work, it will necessary to turn off your water supply at
interval between the hours of 9.00 am and 5.00pm.
The only exception being the cold water tap in your kitchen.
Would you please ensure that all taps in your home are turned off and remain turned off during this period?
If you have central heating, this can be used as normal and will not be affected by this work.
We suggest that you fill your bath with water, which will enable you to manually flush the toilet during the disruption. On completion of the works, service will resume as normal; there is no need to run your taps for a while before using the water again.
For your security all our employees will be carrying their Hertel Services identification.
We would like to take this opportunity of thanking you for your co-operation in this matter and we look to keep the disruption to a minimum, however, should you require any further clarification, or have any doubt to the legitimacy of this letter, please do not hesitate to contact us on the above numbers.
Yours Sincerely,
Paul C Taylor
Account Manager