Residents Newsletter March 2011

Residents Newsletter March 2011The following letter was sent to the residents of the Curnock Estate.

The original document can be found on this link.

 

 


Residents’ Newsletter March 2011

Curnock Street Estate

Welcome to the fifth edition of Apollo’s newsletter for Camden residents at Curnock Street Estate.

Apollo site office
Off Pratt Street
London NW1 OLY
(Situated behind Warmsworth block)
Tel: 02073884448
Fax: 020 7388 4448

Completion dates for works

Due to unforeseen additional necessary works we now hope to complete early July 2011.

We are now renewing all the hot water distribution pipe work to both the Lomax and Camden underground car parks.

We apologise for any inconvenience this may cause.

Important information

In case of an emergency between working hours (Monday to Friday) for the works we are undertaking please call Tony Bowcutt, Site Manager on 07825106790 or the site office on 0207 388 4448. At all other times contact Camden out of hours on 020 7974 4444 or Apollo on 01202 653 293.

Progress of works

The installation of new heating distribution pipe work is now complete to all blocks. The majority of making good to the ground works around the estate are now complete.

Ground works around the Estate

We have also progressed with the installation of new calorifiers (water storage vessels) within the boiler house.

Installation of new calorifiers water storage vessels within the boiler house

The new acoustic screens and doors to the boiler house have been installed.

The new acoustic screens and doors to the boiler house have been installed

We are now working on the installation of the new distribution pipe work and valves to the hot water supply system in both the Camden and Lomax underground car parks.

This will improve the supply of hot water the blocks above these car parks

We will inform residents when the connections between the new pipe work and existing risers
will take place.

The picture below shows a section of pipe removed from the hot water supply pipe work to the Ravenscar block

A section of pipe removed from the hot water supply pipe work to the Ravenscar block

PLEASE BEWARE!

We would like to remind parents that during the works children are their responsibility and that fenced off areas are classed as building sites and not play areas.

All Apollo employees will have an Apollo photo identification card and should be wearing an Apollo high viz jacket with identification numbered on the back.

If you are unsure about a caller to your home you should ask them to wait outside and call any member of the project team.

Weekly Information Surgery

These will now take place every Wednesday at 10am at the site office the RLO and Site Manager will be available to answer any concerns/questions you may have about the works.